Lockdown and social distancing have provided businesses with many challenges this year. The Penny Nuclear team have turned this challenge into an opportunity to improve the way in which they offer Factory Acceptance Testing.

With unprecedented numbers of people working from home or under restricted travel, physical travel to witness FAT has been difficult. The Penny Nuclear team utilised a high-resolution CCTV system inside the nuclear work area to record, live stream and present the product in use to its customers.

The images below show FAT of a 300-tonne hydraulic drum compactor, used to compress drums of Fuel Element Debris (FED) which is to be retrieved at Magnox’s Hinkley Point A site.

With this being a key project for Magnox, if the completion of the FAT was not possible until travel restrictions were lifted, this would have put the project on hold until potentially 2021.

‘We set up our CCTV system to capture key parts of the systems that were developed for waste handling and storage’, says Simon Pykett, General Manager of Penny Nuclear. ‘This enabled us to provide our customers with a split-screen view of the entire system being demonstrated and to pass FAT. This ultimately led to us being able to successfully demonstrate the capabilities of the equipment to the customer and progress to the next stage of the project.’

Keeping Business Moving Throughout Lockdown and Beyond

The adaptation of the FAT has allowed Penny Nuclear to continue to deliver solutions to its customers, enabling our customers to continue to work on their decommissioning projects.

The CCTV has also been utilised to help the project engineers to test a remote puck loading system. The high-resolution CCTV feed is streamed onto a laptop and is used to position the puck into a repository behind a screen that imitates a shield wall.

The Penny Nuclear team plan to continue to use this method of demonstrating the product throughout the pandemic and beyond. ‘You could argue that the video actually worked better than an in-person demonstration’ says Penny Nuclear Project Engineer Rob Stuart. ‘Our customer could view the whole system and key elements working together, as well as pause and rewind the video to pick out key moments of the test. The enhanced viewing experience could even potentially help us to identify improvements to systems for the future.’

Penny Nuclear Logo

About Penny Nuclear

Penny Nuclear is a tier 2 supplier to the nuclear industry supplying directly to companies such as Sellafield Ltd and Magnox Ltd amongst others

Penny Nuclear designs and manufactures lifting equipment, mechanical handling solutions and hydraulic systems for all stages of the nuclear plant lifecycle and nuclear fuel cycle. Whether it is for decommissioning, generating, research or new build sites, we have the knowledge and experience to provide you with robust, cost-effective solutions within extremely competitive lead times.

Want to know more?

Get in touch

Related Products

Accreditations

LEEA Development Member - Penny Hydraulics

LEEA Development Member

UVDB Qualified - Penny Hydraulics Ltd

UVDB Qualified

NDA Supply Chain Charter - Penny Hydraulics Ltd

NDA Supply Chain Charter

- Penny Hydraulics Ltd

Fit 4 Nuclear

- Penny Hydraulics Ltd

ISO 14001:2015

ISO 9001:2015 Quality Management - Penny Hydraulics Ltd

ISO 9001:2015 Quality Management

EN1090 - Penny Hydraulics Ltd

EN1090

Get in touch with our team

Subscribe to our mailing list

arrow_upward